P6 Activity Won’t Schedule On Time

We received a call at 4pm on Friday afternoon (the obligatory Friday Afternoon Construction Emergency) concerning a scheduling issue: in spite of all attempts, a 10 day P6 activity with only 2 days remaining was showing a disconnected duration, a gap of 2 months between its Actual Progress and its Finish date. Worse, important Successor Activities were linked to the delayed Activity , so the whole logical path was being held hostage by the rogue activity. Try as I might, using all the tricks I know for manually controlling & updating progress, every time I scheduled the project, the Activity would disconnect from its progressed status, and show the same 2 month gap. I changed Duration type to Physical, manually edited Remaining Early Start, all to no avail. It looked like a classic case of Out of Sequence Activity, but all its Predecessors were 100% complete, so that seemed illogical. I should have run the Schedule Log report to check for Out of Sequence, but I kept thinking that if I kept at it, the solution would reveal itself. As usual, I should have listened to that little voice. Any time a progress bar displays a disconnect between Actual Progress & Remaining Duration, it’s bound to be a case of Out of Sequence work.

The Solution: One of two methods: 1) in Schedule Options, change the default setting from Reatained Logic to Progress Override. or 2) Change the Predecessor-Sucessor logic to reflect the new relationships by. Out of Sequence work cannot be scheduled until all its Predecessors have bee n satisfied. Even if Predecessors are Completed, an Activity can’t logically finish if those Predecessors have unsatisfied logic prior. We opted for option 1, a simpler course of action. And it worked! We were out of the office by 5. Let the weekend commence!

Related posts

Estimating Controls

Does this sound familiar at your company? 1. Bids are time‐consuming 2. Job costing is tedious 3. We’re too busy to change now‐ and besides

Read More »